Meekatharra

Project Name: Meekathara
Location: Meekathara, WA
Client: Water Corporation
Battery: 115kWh
Solar DC PV: 303kWp
Thermal Diesel: 2 x 200kVA

Hybrid Systems was engaged by Guidera O’Connor for the design, manufacturing, installation and commissioning of a hybrid renewable energy system for the Water Corporation Wastewater Treatment Plant (WWTP) located at Meekatharra, in the remote Mid-West region of Western Australia.

The system can operate as either grid connected or as an islanded off-grid system and included a 115kWh BESS, 303kWp of Solar and 2 2 x 200kVA Diesel generators. A key benefit for Water Corp includes the ability to disconnect from the grid and operate the system in hydrocarbon off during sunlight hours reducing both carbon emissions and costs.